January 19, 2026

Bathroom Remodel Timeline for Rockford Homeowners

A guest bath usually takes 3 weeks on site. A master bath with a custom tile shower usually takes 5. Here's what actually happens.

Week 1: demo & rough-in. Old tub, tile and vanity out. Plumber roughs new supply and drain lines. Electrician relocates outlets and lighting.

Week 2: waterproofing & tile prep. Schluter waterproofing over the shower assembly. Backer board, cement, moisture barrier.

Week 3: tile. Floor, walls, shower. This is the longest single trade on the job.

Week 4: vanity, fixtures, paint. Vanity set, top installed, fixtures hung, walls painted, trim finished.

Week 5: punch list. Anything that wasn't perfect gets fixed before we hand you the keys.